CONSTRUCTION UPDATES

Over the next few years, the site at 4500 rue Hochelaga will gradually evolve, and we are delighted to announce the start of work on the first phases of the project!

 

Throughout this development, we will keep you informed of progress on this page, which will be regularly updated to allow you to follow the progress of the work and obtain information on our schedule.

 

Whether you are a loyal resident, an occasional visitor or simply curious about our project, you are welcome to explore this page. So don't hesitate to come back often for the latest news!

DEMOLITION

March 2023 - Completed

01

DECONTAMINATION

Summer 2023 - Completed

02

The decontamination of a portion of the site will take place during the summer of 2023. The mobilization of our teams of workers is scheduled for the week of June 26, 2023, and will last approximately two months. Our teams are dedicated to ensuring that the site is clean, safe, and complies with all current environmental standards. During this decontamination period, you may notice an increase in truck traffic. However, since the majority of operations will be carried out from the site itself, this construction phase should not cause any changes to the current commuting habits of the residents in the neighborhood.

EXCAVATION

Summer / Fall 2023 - Ongoing

03

Blasting work will take place during the day, from Monday to Friday, between 7:00 AM and 5:00 PM, and the daily number of blasts may vary depending on the progress of the work.

FORMWORK AND CONCRETE

Fall 2023 - Spring 2024

04

ENVELOPE WORK

Winter 2024

05